Yesterday in El-Ad West LLC v. Zurich American Ins. Co., 2015 WL 4078762, 2015 N.Y. App. Div. LEXIS 5753 (N.Y.App.Div., Jul. 7, 2015), a unanimous panel of New York’s intermediate level appellate court held that a flood sub-limit capped all loss caused by flood, without regard to whether it was physical damage to property or a “downstream” financial loss such as delay in completion. In the words of the opinion, reading the contract of insurance in such a way as to find that the flood sub-limit did not apply to delay in completion losses “would render the flood limit meaningless with respect to that coverage.” The panel thereby affirmed a Superstorm Sandy decision that we reported on in July of…